HomeNewsPJM Capacity2028/2029 Auction Results
Official Result
PJM • Capacity MarketUpdated July 14, 2026

PJM 2028/2029 Capacity Auction: $325 Cap, 6.8 GW Shortfall

The Bottom Line (PJM Capacity)

PJM's 2028/2029 Base Residual Auction cleared 138,317.8 MW at the $325/MW-day cap. Including FRR commitments, PJM procured 149,181.6 MW—6,831.3 MW below the reliability requirement. PJM says this is the second straight material reserve shortfall; it raises reliability and procurement risk but does not determine any customer's delivered rate.

$325
Clearing Price
Per MW-day across all modeled LDAs
138.3 GW
RPM Capacity
138,317.8 MW UCAP cleared
6.8 GW
Reliability Gap
6,831.3 MW UCAP below requirement

What PJM Reported

PJM's July 14 report says the 2028/2029 auction cleared 138,317.8 MW UCAP through the Reliability Pricing Model. Fixed Resource Requirement entities committed another 10,863.8 MW UCAP, bringing total procured capacity to 149,181.6 MW UCAP.

That total was 6,831.3 MW UCAP below the RTO Reliability Requirement. PJM reports a 14.4% RPM installed reserve margin and a 14.7% total reserve margin, versus the 20% target used to support the one-day-in-10-years reliability criterion.

High Prices Persisted Even As More Capacity Cleared

Every modeled LDA cleared at the $325/MW-day auction cap, with no constrained LDAs. The clearing price was 2.5% below the prior auction's $333.44/MW-day cap, while PJM says cleared RPM capacity increased by 3,733.2 MW UCAP.

The improvement did not close the resource gap. PJM's reliability requirement rose from 152,400 MW to 156,013 MW UCAP, including a 1,374.5 MW increase in forecast load that PJM says was driven largely by additional large loads. Only 524.7 MW UCAP of new generation and uprates cleared.

What The Result Does Not Tell You

A $325/MW-day RTO result is not an account-level bill quote. Supplier terms, PLC, zone, tariff class, utility riders, hedges, and load shape determine how capacity costs reach a commercial account. PJM also cautions that its $16.4 billion cleared-MW-times-price indicator is not the same as total cost to load.

2028/2029 Auction Result At A Glance

ItemOfficial ValueBuyer Read
RTO clearing price$325/MW-dayEvery modeled LDA cleared at the auction cap, down 2.5% from $333.44/MW-day for 2027/2028.
RPM capacity cleared138,317.8 MW UCAPPJM cleared more RPM capacity than in the prior auction, but not enough to meet the reliability requirement.
RPM plus FRR capacity149,181.6 MW UCAPThis total remained 6,831.3 MW UCAP below PJM’s RTO Reliability Requirement.
Total reserve margin14.7%PJM reports a total reserve margin 5.3 percentage points below the 20% target.
New generation and uprates524.7 MW UCAPThe auction cleared 317.1 MW from new generation and 207.6 MW from uprates.
Auction value indicator$16.4 billionPJM says cleared MW multiplied by clearing price was unchanged from the prior auction; this is not the same as total cost to load.

Why The Reliability Gap Matters

PJM says a shortfall does not mean the grid will necessarily fail to serve load in 2028/2029. It means the system would operate with slimmer reserves and greater risk. This is the second consecutive auction to clear more than one percentage point below the installed reserve margin target.

PJM's current tariff language references three consecutive qualifying auctions for a Reliability Backstop Auction trigger. Buyers should therefore track the active stakeholder process and future auction results rather than treating this second shortfall as proof that every backstop step is automatic or complete.

Commercial Buyer Action List

Decision AreaCurrent StatusNext Step
Capacity pass-through exposureReview contract languageConfirm whether capacity is fixed, passed through, reconciled later, or embedded in a utility or supplier rider.
PLC and peak managementModel account exposureThe auction price is regional; each account’s capacity obligation still depends on load shape, PLC, zone, tariff, and contract terms.
Demand responseEvaluate economics carefullyHigh capacity values can support flexible-load economics, but CSP terms, metering, penalties, dispatch rules, and availability still govern net value.
Reliability backstopWatch PJM follow-throughThis is the second straight material reserve shortfall; track the stakeholder process rather than assuming the tariff trigger has already been reached.

What To Watch Next

  • PJM's Reliability Backstop Procurement and Connect & Manage stakeholder work.
  • Whether incremental auctions, new entry, uprates, imports, or forecast revisions narrow the 2028/2029 gap.
  • Supplier and utility filings that translate wholesale capacity costs into specific tariffs or contract charges.
  • Account-level PLC and demand-response economics before the June 2028 delivery year begins.

Next buyer check

Map the official auction result to contract language, PLC, tariff treatment, and flexible-load capability.

PJM Topic Hub

Sources: PJM, “2028/2029 Base Residual Auction Report,” July 14, 2026; PJM Capacity Market (RPM) delivery-year archive; PJM Inside Lines auction-opening and price-collar notices.

📬Free Intelligence

Free Energy Market Pulse — Every Tuesday

Join energy professionals getting weekly rate alerts, gas forecasts, and procurement intel.

No spam. Unsubscribe anytime. Data never shared.

Translate The Auction Result To Your Account

The $325/MW-day result is public. Contract pass-through language, PLC, tariff treatment, and demand-response capability determine the account-level exposure.