PJM Capacity Auction History

Historical clearing prices for the PJM Base Residual Auction (BRA). Understand the market cycles and the unprecedented volatility of the 2026/2027 delivery year.

RTO Clearing Prices ($/MW-day)

$164.77
2018/2019
$100.00
2019/2020
$76.53
2020/2021
$140.00
2021/2022
$50.00
2022/2023
$34.13
2023/2024
$28.92
2024/2025
$28.92 (Delayed)
2025/2026
$269.92 (Record)
2026/2027

📈 The 2026/2027 Spike

Prices jumped 833% from $28.92 to $269.92 due to significant retirements of coal generation and a sharp increase in forecasted load from data centers. PJM's new risk modeling also de-rated the capacity value of intermittent resources.

🔮 Future Outlook

Analysts project capacity prices to remain elevated near $150-$200/MW-day for the 2027/2028 auction. The structural supply-demand tightness will take years to resolve through new transmission and generation build-out.

Detailed Auction Results

Delivery YearRTO Price ($/MW-day)YoY ChangeStatus
2026/2027$269.92+833%Record High
2025/2026$28.92-15%Delayed Auction
2024/2025$28.92-15%Historic Low
2023/2024$34.13-32%Low Volatility
2022/2023$50.00-64%Price Correction